The city of Lawrence is about to start construction on bus stops all over town. Many stops will be getting shelters and benches, but the work might complicate things for riders in the short term.
Four or five stops will be completed each week of July until the work is done, according to the Lawrence Transit website.
The dates below may change because of weather or other circumstances, but here’s the tentative schedule from the website:
Phase 1: July 6 – July 10
• 4th and Maine Northbound (Route 3, Stop 150)– Drivers can pickup and drop after construction before turn onto Missouri
• 12th and Haskell Northbound (Route 1, Stop 368) – Drivers can pickup and drop before the construction
• 6th and Wisconsin Eastbound (Route 6, Stop 180) – Drivers can pickup and drop before construction at Dollar General
• 19th and Massachusetts Southbound (Route 7, Stop 365) – Drivers can pickup and drop after construction
Phase 2: July 12 – July 17
• 27th and Iowa (Eastbound)
• 27th and Redbud (Eastbound)
• 25th and Louisiana
• 31st and Nieder
Phase 3: July 19 – 24
• 21st and Stewart
• Wakarusa and Harvard
• Clinton Parkway and Crossgate
• Clinton Parkway and Hartford
• Clinton Parkway and Kasold
Phase 4: July 26 – July 31
• 27th and Iowa
• 27th and Redbud
• 31st and Harrison
• 27th and Holcom
Lawrence Transit has a mobile app to stay up to date on bus stops and routes. Find more info about that at this link.
You can also call 785-864-4644 for the latest information on bus routes, and/or follow Lawrence Transit on Facebook and Twitter.